March 18, 2013

 

COMMUNITY AND ECONOMIC DEVELOPMENT

 

ENGINEERING

 

S AND L LANDSCAPING AND EXCAVATING; EXCAVATION; ON CALL TASK ORDER; GENERAL CONSTRUCTION; TASK ORDER PROJECT; FIRE STATION NO. 6; DRIVE APPROACH RECONSTRUCTION; 948 WEST; 800 SOUTH

Amendment No. 3: Amends agreement with S and L Landscaping and Excavating, Inc. dated January 20, 2012 relating to on-call task order projects – Fire Station No. 6 drive approach reconstruction at 948 West 800 South; Contract No. 06-2-12-5731-3.  C 12-29

 

ROCKY MOUNTAIN POWER; RMP; CUSTOMER REQUESTED WORK AGREEMENT; 655 EAST; 2250 SOUTH; RELOCATE POWER POLES; POLE RELOCATION

Agreement: Allows Rocky Mountain Power to relocate two power poles and associated equipment at approximately 655 East 2250 South; Contract No. 06-2-13-6485.  C 13-145

 

ROCKY MOUNTAIN POWER; RMP; CUSTOMER REQUESTED WORK AGREEMENT; REMOVE POLE; TRANSFER CONDUCTORS; 970 EAST; 2250 SOUTH

Agreement: Allows Rocky Mountain Power to remove one pole and transfer secondary/service conductors at approximately 970 East 2250 South; Contract No. 06-2-13-6486.  C 13-146

 

ROCKY MOUNTAIN POWER; RMP; ESTIMATING AGREEMENT; RELOCATION WORK; REMOVE AND REPLACE CERTAIN FACILITIES; 700 SOUTH REHABILITATION

Agreement: Allows Rocky Mountain Power to estimate costs to remove and replace certain existing facilities; Project No. 102165, Contract No. 06-2-13-6490.  C 13-147

 

MET WST UT QRS 16-97; RIGHT-OF-WAY AGREEMENT; METRO WASTE; GLADIOLA STREET; 900 SOUTH; DEDICATION PAYMENT

Agreement: With MET WST (UT) QRS 16-97, Inc. relating to right-of-way dedication payments; Contract No. 06-2-13-6481.  C 13-148

 

HOUSING AND NEIGHBORHOOD DEVELOPMENT

 

MOCA SYSTEMS; PROFESSIONAL SERVICES AGREEMENT; PROJECT MANAGEMENT SERVICES; EVIDENCE STORAGE AND CRIME LAB; PUBLIC SAFETY BUILDING

Agreement: Moca Systems, Inc. will provide project management services for development/construction of evidence storage/crime lab for the Public Safety Building; Contract No. 06-1-13-6479.  C 13-149

 

PROPERTY

 

KINGFISHER CAPITAL; EASEMENT PURCHASE AGREEMENT; 1291 SOUTH; 1100 EAST; PERPETUAL TRAFFIC SIGNAL; UPGRADE; 11TH EAST; 13TH SOUTH

Easement Purchase Agreement: Salt Lake City Corporation will purchase a perpetual traffic signal easement from Kingsfisher Capital, LLC for property located at approximately 1291 South 1100 East; Contract No. 06-9-13-6478.  Cross Reference W 13-16.  C 13-150

 

EASEMENT; KINGFISHER CAPITAL; EASEMENT PURCHASE AGREEMENT; 1291 SOUTH; 1100 EAST; PERPETUAL TRAFFIC SIGNAL; UPGRADE; 11TH EAST; 13TH SOUTH

Easement: From Kingsfisher Capital, LLC relating to a perpetual traffic signal easement located at approximately 1291 South 1100 East; Contract No. 06-9-13-6478.  Cross Reference C 13-150.  W 13-16

 

POLICE

 

UNIVERSITY OF UTAH; UOFU; U OF U; INTERMOUNTAIN INJURY CONTROL RESEARCH; SALT LAKE TICKETING AGGRESSIVE CARS AND TRUCKS EVALUATION

Agreement: The University of Utah will provide research studies and reporting services; Contract No. 02-1-13-6225.  C 13-151

 

PUBLIC UTILITIES

 

SEA REACH; VISITOR CENTER EXHIBITS; SILVER LAKE VISITOR CENTER; BIG COTTONWOOD CANYON SCENIC BYWAY

Agreement: Sea Reach, Ltd. will provide exhibits at Silver Lake Visitor Center - Big Cottonwood Canyon Scenic Byway; Contract No. 51-1-13-6449.  C 13-152

 

RELEASE OF NOTICE OF INTEREST; 1770 EAST; HOLLADAY BOULEVARD; BLVD; QUIT CLAIM DEED; QCD

Release of Notice of Interest: Relating to Quit Claim Deeds recorded with Salt Lake County on February 12, 1881, July 30, 1992 and August 7, 1995 for property at 1770 East Holladay Boulevard (Release recorded 2-13-13.  W 13-15

 

HOLLAND AND HART; LEGAL ENGAGEMENT; ASSISTANCE; MISCELLANEOUS ENVIRONMENTAL MATTERS; NOTHWEST OIL DRAIN CANAL

Agreement: Holland and Hart, LLP will provide various miscellaneous environmental matters including Northwest Oil Drain Canal; Contract No. 51-1-13-6495.  C 13-153

 

PROJECT ENGINEERING CONSULTANTS; PROFESSIONAL SERVICES AGREEMENT; ORANGE STREET PHASE 2; PHASE II; SEWER REHABILITATION; DESIGN; NORTH TEMPLE; CALIFORNIA AVENUE; TRUNK LINE

Agreement: Project Engineering Consultants, Ltd. will provide Orange Street - Phase 2 sewer rehabilitation design - 42” trunk line on Orange Street from North Temple to California Avenue; Project No. 525002576, Contract No. 51-1-13-6496.  C 13-154

 

sc

 

SUGAR HOUSE STREETCAR EXTENSION ALTERNATIVES; CIRCULATION AND STREETSCAPE AMENITIES PLAN; SUGARHOUSE; STREET CAR; LOCALLY PREFERRED ALTERNATIVE

An ordinance and resolution the Sugar House Streetcar Extension alternatives and the Circulation and Streetscape Amenities Plan including expansion of the Monument Plaza, realignment of Sugarmont and Wilmington, reduction of traffic lanes on Highland Drive, division of large blocks, addition of bicycle lanes on 2100 South, and connecting Parley’s Trail between the Fairmont Aquatic Center and Hidden Hollow. This plan would be an implementation tool for the goals adopted in the Sugar House Master Plan.  P 13-4

 

ZONING AMENDMENT; MICHAEL LOBB; 1321 SOUTH; 500 EAST STREET; CN; NEIGHBORHOOD COMMERCIAL; ELIMINATE CERTAIN COVENANTS, CONDITIONS AND RESTRICTIONS; CCRS

An ordinance amending the zoning of the property located at 1321 South 500 East Street to eliminate certain covenants, conditions and restrictions (CCRs) recorded against and associated with the Neighborhood Commercial (CN) zoning, Petition No. PLNPCM2012-00588.

P 13-5