January 16, 2012

 

AIRPORT

 

CARPET REPLACEMENT; DIVERSIFIED FLOORING; AIRPORT TERMINALS

Agreement:  With Diversified Flooring for carpet replacement in airport terminals; Project No. 5421221304, Contract No. 54-2-12-5652. C 12-25

 

HANGAR LEASE; SHADE HANGAR; SOUTH VALLEY REGIONAL AIRPORT; DANIEL LIGHTEN; ROW D, HANGER 14; SVRA

Hangar Lease:  Lease agreement with Daniel Lighten at the South Valley Regional Airport for shade hangar 14, row D.  C 12-26

 

HMS HOST; TEMPORARY OFFICE; HOST INTERNATIONAL; LEASE SPACE; CONCESSION; SALT LAKE INTERNATIONAL AIRPORT

Temporary Office Space Lease:  With Host International to accommodate the development and construction of the Airport’s Concessions Program.  C 12-27

 

ATTORNEY

RECORDER

 

SUGAR HOUSE COMMUNITY COUNCIL; REGISTERED ORGANIZATION; ARTICLES OF INCORPORATION; CURRENT OFFICERS; MEETING DATES; ARTICLES OF INCORPORATION; BYLAWS

Sugar House Community Council:  Officers, meeting dates, articles of Incorporation and Bylaws. Cross Reference C 04-20.  G 12-9

 

COMMUNITY AND ECONOMIC DEVELOPMENT

 

ENGINEERING

 

KEVIN STEPHENS CONSTRUCTION; ON CALL TASK ORDER; GENERAL CONSTRUCTION; TASK ORDER PROJECT

Agreement:  With Kevin Stephens Construction for on call task order projects; Project No. 300098, Contract No. 06-2-12-5735.  C 12-28

 

S AND L LANDSCAPING AND EXCAVATION; ON CALL TASK ORDER; GENERAL CONSTRUCTION; TASK ORDER PROJECT

Agreement:  With S and L Landscaping for on call task order projects; Contract No. 06-2-12-5731.  C 12-29

 

MODERN ROOFING AND CONSTRUCTION; ON CALL TASK ORDER; GENERAL CONSTRUCTION; TASK ORDER PROJECT

Agreement:  With Modern Roofing and Construction for on call task order projects; Contract No. 06-2-12-5732.  C 12-30

 

IMS INFRASTRUCTURE MANAGEMENT SERVICES; PAVEMENT CONDITION INVENTORY; 595 CENTERLINE MILES; SALT LAKE CITY STREETS

Agreement:  With IMS Infrastructure Management Services for pavement condition inventory of 595 centerline miles of Salt Lake City streets; Contract No. 06-2-12-5722.  C 12-31

 

PROPERTY MANAGEMENT

 

POPLAR GROVE PARK; QCD; QUIT CLAIM DEED; PARK HOUSE; NEIGHBORHOOD DEVELOPMENT; 1189 WEST; 700 SOUTH

Quit Claim Deed:  For Poplar Grove Park house at 1189 West 700 South to Neighborhood Development; Contract No. 06-8-12-5723.  W 12-9

 

FINANCE

PURCHASING

 

SUNGARD PUBLIC SECTOR; INTEGRATED FINANCIAL ACCOUNTING SYSTEM; IFAS

Amendment No. 7: Amends original agreement dated July 3, 2006 with Sungard Data Systems relating to purchase and installation of software for an integrated  governmental financial system; Contract No. 01-1-93-1188-7. Cross Reference C 93-185 and C 09-362.  C 06-429

 

EZLINKS GOLF INC; GOLF RESERVATION CALL CENTER; PRO SHOP SOFTWARE Amendment No. 1:  Amends original agreement dated July 3, 2006 with EZLINKS Golf for a golf reservation call center and software; Contract No. 59-1-11-5056-1. C 11-42

 

PUBLIC UTILITIES

 

WHITAKER CONSTRUCTION COMPANY; BIG COTTONWOOD WATER TREATMENT PLANT BYPASS

Agreement:  With Whitaker Construction for the Big Cottonwood Water Treatment Plant bypass; Contract No. 51-2-12-5736.  C 12-32

 

NOLAND AND SONS CONSTRUCTION; TESORO STORM DRAIN LINE 

Agreement:  With Tesoro for a 24 inch storm drain line at 700 West 1200 North; Project No. 53470665, Contract No. 51-2-12-5730.  C 12-33

 

HIGHLAND PARK GROUP; WATER MAIN REPLACEMENT; CITY MAINTAINED STORM DRAIN MAIN AGREEMENT; 2705 PARLEY’S WAY

Agreement:  With Highland Park Group for a City maintained storm drain and water main replacement at 2705 Parley’s Way; Job No. 513505044, Contract No. 51-2-12-5727.  C 12-34

STATE OF UTAH; DIVISION OF FORESTRY, FIRE AND STATE LAND; EASEMENT; STORM DRAIN CONNECTION; JORDAN RIVER; FOLSOM AVENUE

Easement No. 400-00250:  With the Division of Forestry, Fire and State Land for a storm drain connection to the Jordan River on Folsom Avenue.  C 12-35