MEADOW VALLEY CONTRACTORS; TAXIWAY G EXTENSION; NORTH END; PROJECT NO 5410170276; CONTRACT NO 54-2-97-4468
Agreement: With Meadow Valley Contractors for the Taxiway G extension - north end; the cost is $9,400,000, Project No. 5410170276, Contract No. 54-2-97-4468. C 97-414
HARPER EXCAVATION; DEICING; PIPING; STORAGE; PROJECT NO 5410020282; CONTRACT NO 54-2-97-4502
Agreement: With Harper Excavation for the construction of deicing/piping storage; the cost is $13,682,350, Project No. 5410020282, Contract No. 54-2-97-4502. C 97-415 *Recorded July 22, 1997.
BIDWELL; APRON REPAIR; CONCOURSE B; CONCOURSE C; CONCOURSE D; PROJECT NO 5410160313; CONTRACT NO 54-2-97-4343
Agreement: With Bidwell for the Salt Lake City International Airport apron repair between Concourses B, C, and D; the cost is $295,035.75, Project No. 5410160313, Contract No. 54-2-97-4343. C 97-416 *Recorded July 22, 1997.
COMMUNITY AND ECONOMIC DEVELOPMENT
CAPITAL PLANNING
JACKSON PROPERTY MANAGEMENT; ECONOMIC DEVELOPMENT REVOLVING LOAN FUND; CED; COMMUNITY AND ECONOMIC DEVELOPMENT; URBAN DEVELOPMENT ACTION GRANT; UDAG; ECONOMIC ENHANCEMENT; CITY CAB COMPANY; RESOLUTION 40 OF 1997; CONTRACT NO 06-5-98-4663
Loan Agreement: With Jackson Property Management for the relocation of City Cab Company; the cost is a $75,000 loan from the City’s Economic Development Revolving Loan Fund, Contract No. 06-5-98-4663. Authorized by Resolution 40 of 1997. C 97-370 *Recorded July 22, 1997.
JACKSON PROPERTY MANAGEMENT; ECONOMIC DEVELOPMENT REVOLVING LOAN FUND; CED; COMMUNITY AND ECONOMIC DEVELOPMENT; URBAN DEVELOPMENT ACTION GRANT; UDAG; ECONOMIC ENHANCEMENT; CITY CAB COMPANY; TRUST DEED; CONTRACT NO 06-5-98-4663
Trust Deed: With Jackson Property Management for the relocation of City Cab Company; Contract No. 06-5-98-4663. W 97-1 *Recorded July 22, 1997.
PLANNING AND ZONING
BURLINGTON ADDITION; GLENDALE PARK SUBDIVISION; HABITAT FOR HUMANITY; FINAL PLAT
Final Plat: Amended Burlington Addition to the Glendale Park Subdivision. W 97-5
POLICE DEPARTMENT
BILL PHILLIPS; CHAPLAIN; CHAPLAINS CORPS; CONTRACT NO 02-1-98-4629
Agreement: Bill Phillips will volunteer for the Police Chaplain’s Corps; Contract No. 02-1-98-4629. C 97-417 *Recorded July 25, 1997.
PUBLIC SERVICES
ENGINEERING DEPARTMENT
FFKR ARCHITECTURE; F F K R ARCHITECTURE; RECREATION CENTER; ICE SHEET EXPANSION; STEINER AQUATIC CENTER; FOOD FACILITY; CONCESSION; JOB NO 660401; CONTRACT NO 03-2-97-4090-1
Amendment No. 1: With FFKR Architecture for the design of the ice sheet expansion at Steiner Aquatic Center; the cost is $9,835, Job No. 660401, Contract No. 03-2-97-4090-1. C 96-797 *Recorded July 25, 1997.
EMCON ASSOCIATES; LANDFILL MODULES; MASTER PLAN; SLOPE STABILITY ANALYSIS; JOB NO 40-B-17, CONTRACT NO 03-2-92-1127-4
Amendment No. 4: With Emcon Associates for a slope stability analysis for the landfill modules; the cost is $12,000, Job No. 40-B-17, Contract No. 03-2-92-1127-4. C 92-432 *Recorded July 25, 1997.
PUBLIC UTILITIES
BELL CANYON CONSTRUCTION; WATERMAIN REPLACEMENT; ALOHA DRIVE; I STREET; NORTHCREST DRIVE; PROJECT NO 513504565; NORTHMONT AVENUE; 444 EAST; 650 EAST; PROJECT NO 5135028191; CONTRACT NO 51-2-98-4644
Agreement: With Bell Canyon Construction for 8-inch watermain replacements on Aloha Drive - I Street to Northcrest Drive; Project No. 513504565 and Northmont Avenue - 444 East to 650 East, Project No. 5135028191, the cost is $144,070.70, Contract No. 51-2-98-4644. C 97-418
DEAN MAYBERRY CONTRACTOR; METAL BUILDING PUMP HOUSE; WATER TREATMENT PLANT; CONTRACT NO 51-1-97-4533
Agreement: With Dean Mayberry Contractor for a metal building pump house at the water treatment plant; the cost is $12,875, Contract No. 51-1-97-4533. C 97-419
ALDER CONSTRUCTION; DETECTOR CHECK CONNECTION; 1160 SOUTH PIONEER ROAD; PETITION NO. 1100-97-867
Agreement: With Alder Construction Company for an 8-inch detector check connection for the property located at 1160 South Pioneer Road; Petition No. 1100-97-867. C 97-420 *Recorded July 3, 1997.